How to Do a Deficiency Walk-Through on a New Home in BC
You've waited months, sometimes years, for your presale or new home. The deficiency walk-through, also called the pre-delivery inspection or PDI, is your last look before you take the keys. This guide covers what it is, why it matters more than most buyers think, what to bring, how to walk it room by room, and what to do after you sign.
Quick Answer
A deficiency walk-through is a joint inspection of your new home with the builder's representative, usually shortly before completion or possession. Together you list everything that's damaged, unfinished or not working, and both of you sign the list. To do it well: bring painter's tape, a phone with a flashlight and a charger to test outlets, your contract's finish and upgrade list, and a second set of eyes. Work one room at a time, top to bottom: ceilings, walls, trim, floors, then everything that opens, turns on or drains. Look at every surface at an angle with your flashlight. Write each item with its exact location, and photograph it. For some homes, it's worth doing it in two passes: a professional inspection before you remove subjects, then one more walk-through about 10 days before possession. It matters because cosmetic damage you don't list before move-in is hard to claim later: BC's warranty rules let a warranty provider exclude damage caused by an owner or a third party, such as movers. Your 2-5-10 home warranty still covers real defects after you move in. Most defects in materials and labour are covered for 12 months, so keep a running list and put claims in writing before coverage ends.
Buying a presale or a brand-new home? Book a 20-minute strategy call and we'll go over your completion timeline and what to watch for.

What a deficiency walk-through is
Builders call it different things: a deficiency walk-through, a pre-delivery inspection (PDI), a pre-occupancy inspection or a homeowner orientation. It's the same appointment. A representative of the builder walks the home with you, shows you how the systems work, and records anything that needs attention on an inspection report. You both sign it, and the builder works through the list.
Two things surprise most buyers:
- It isn't set by the warranty regulation. B.C.'s Homeowner Protection Act Regulation sets the minimum 2-5-10 warranty coverage, but it doesn't require a pre-delivery inspection or say how one must work. The walk-through is standard practice for builders and is usually described in your purchase contract or homeowner manual. So the timing, the form and whether you can bring an inspector all depend on your builder. Ask early.
- It's often your first time inside the finished home. On a presale, you may have last seen the home as a floor plan and a display suite. The walk-through is where you compare what was promised with what was built.
Why it matters more than most buyers think
Your new home comes with B.C.'s mandatory 2-5-10 home warranty, so it's tempting to treat the walk-through as a formality. Here's why it isn't.
The list is your baseline. The warranty regulation lets a warranty provider exclude "any damage to the extent that it is caused or made worse by an owner or third party." Once you've moved in, a chipped countertop, a gouged floor or a dented door could just as easily have been the movers. If it's on the signed list from before you moved in, there's no question about when it happened. That's why a deficiency walk-through is mostly about the cosmetic items: they're the hardest to claim later.
The clock may already be running. For a home in a strata, warranty coverage on your unit starts on the earlier of when you move in or when legal title transfers to you. Coverage on the building's common property starts when the first home in that building starts its coverage. If you're among the last owners to complete in a building, some of the common-property coverage has already been used up by the time you get your keys.
The 2-5-10 warranty at a glance
| Minimum coverage | What it covers |
|---|---|
| 12 months | Any defect in materials and labour (15 months for strata common property) |
| 24 months | Defects in the electrical, plumbing, heating, ventilation and air conditioning systems; defects in exterior cladding, caulking, windows and doors that could lead to detachment or material damage; and defects that make the home unfit to live in |
| 5 years | Defects in the building envelope, including water penetration |
| 10 years | Structural defects |
Source: Homeowner Protection Act Regulation, Schedule 3. These are the legal minimums; some policies offer more. Check your own warranty certificate for your dates and limits.
Notice what the warranty isn't built for: weathering, normal wear and tear, and damage caused by owners or third parties are all permitted exclusions. That's the gap the walk-through fills.
My approach: two passes, then the one-year list
One walk-through rarely catches everything. For some homes, I recommend splitting it into stages:
- Inspect before you remove subjects. On a newly built home you're buying with subjects, it's worth booking a professional inspection before you go firm. That gets the first round of deficiencies documented early, so the builder can start working through them.
- Go back about 10 days before possession. Once that first round is finished, walk the home one more time. Check that the repairs were done properly, and catch everything else you can.
- Don't worry about what you miss. If you don't get them all, flag them for your one-year. Keep a running list as you live in the home, and send it in writing before your 12-month coverage ends.
With a smaller builder, meet them. If it's a smaller developer, the walk-through is a great time to meet the builder or developer in person and establish rapport. That relationship pays off most for the later deficiencies, the ones that show up in your first year.
On a presale, you're usually already committed by the time the home is finished, so the builder's pre-delivery inspection is your first pass. Ask whether it can be scheduled with enough time for a second look before you move in.
Before the day: how to prepare
The best walk-throughs are won before you arrive. A week or two out:
- Confirm the details in writing. Ask the builder how long the appointment runs, whether the power and water will be on, and whether you can bring a home inspector or a second person. Some builders welcome inspectors at the walk-through and some only allow them afterwards. Better to know now than at the door.
- Pull out your paperwork. Your purchase agreement, the disclosure statement, your colour and finish selections, and every upgrade you paid for. You'll check the home against these.
- Book daylight if you can. Natural light shows paint and drywall flaws. If your slot is late in the day in a Tri-Cities November, your flashlight matters even more.
- Plan for time. Don't book anything right after. Rushing is the most common reason items get missed.
What to bring
- A roll of painter's tape, ideally a bright colour. Tape every item as you find it, so you and the builder's rep can see the whole picture as you go, and so trades can find each spot later.
- Your phone, charged, to photograph each item and to use as a flashlight. A separate flashlight is even better.
- A phone charger or a plug-in outlet tester, to check that every outlet works.
- A notepad or a printed floor plan, to note each item by room.
- A tape measure, to confirm appliance openings, closet depths or anything you plan to fit.
- A second person. One of you looks while the other writes. Two sets of eyes catch more.
How to walk it: a system that catches more
The trick is to be methodical rather than wandering from room to room as things catch your eye.
- One room at a time. Finish a room completely before you move on.
- Top to bottom. Ceiling, walls, trim and doors, then floor. Then everything that opens, turns on or drains.
- Look at an angle. Hold your flashlight flat against a wall or floor and look along the surface. Raking light shows ridges, patches, dents and scratches you'll never see looking straight on. The patch in the photo above is a good example.
- Touch and test. Open and close every door, drawer and window. Turn on every tap and light. Flush every toilet.
- Tape it, photograph it, write it down. Every item, every time, before you move on.
The room-by-room checklist
Every room: ceilings, walls and trim
- Drywall: patches that aren't sanded smooth, nail pops, cracks, dents and visible seams
- Paint: missed spots, drips, roller marks, uneven sheen, paint on hardware or flooring
- Ceiling fixtures, pot lights and cover plates sitting flush and secure
- Baseboards, casings and crown: gaps, open joints, missing caulking, dings
- Outlet and switch covers: straight, secure, not cracked or painted over


Left: a ceiling cover plate that isn't sitting flush. Right: three small marks on one stairwell wall, cap and baseboard. Stairwells take a beating during construction, so slow down there. From a recent deficiency walk-through.
Floors and stairs
- Scratches, dents, chips and gaps in hardwood, laminate or vinyl plank
- Cracked, chipped or uneven tile, and missing or cracked grout
- Carpet seams, stains and loose edges
- Stair treads and nosings for chips; railings and handrails solid, with no wobble
- Squeaks or soft spots as you walk
Kitchen
- Countertops: chips, scratches, seams, and the edge profile you chose
- Cabinet doors and drawers: aligned, closing smoothly, soft-close working, no scratched or chipped finish
- Every appliance: model matches your contract or upgrade list, no dents or scratches, powers on, door seals intact
- Sink and faucet: hot and cold, no drips, and look under the sink for leaks
- Range hood fan and light working
Bathrooms and laundry
- Run every tap, shower and tub. Check water pressure and that hot water arrives.
- Flush every toilet and check it's secure to the floor
- Caulking around tubs, showers, sinks and backsplashes: continuous, with no gaps
- Glass shower doors: no scratches, closing and sealing properly
- Fans running; mirrors and vanity tops undamaged
- Laundry hookups and dryer vent in place
Windows and doors
- Every window opens, closes and locks. Look for scratched glass, broken seals and torn screens.
- Interior doors swing without rubbing and latch properly; stoppers in place
- Exterior doors seal, lock and close without catching; check weatherstripping
- Sliding doors run smoothly and lock
Electrical, heating and mechanical
- Every outlet works (plug in your charger or tester), including the GFCI outlets in kitchens and bathrooms
- Every light and switch works; dimmers dim
- Heating and, if included, air conditioning turn on; thermostats respond
- Ask for a walk-through of the electrical panel, the water shut-off, the hot water system and the ventilation system, and their filters. Take notes. You'll need these on a bad day.
Garage, balcony and exterior
- Garage slab: cracks, stains, and leftover drill holes or anchors
- Garage door opens and closes smoothly, with remotes
- Balcony or deck: membrane or surface undamaged, railings solid, drainage clear
- Exterior: siding, trim and caulking around windows and doors; downspouts connected
- Hose bibs and exterior lights working

Does it match what you bought?
This is the step people skip. With your finish selections and upgrade list in hand, confirm the flooring, cabinet colour, countertop, hardware, light fixtures, appliances and any paid upgrades are what you chose and paid for. A wrong finish is far easier to raise now than after you've lived with it for a month.
Writing the list so it actually gets fixed
The trades who fix your items weren't at your walk-through. Your list is all they have. Make each item specific:
- Vague: "Scratch on counter."
- Specific: "Kitchen island, left of sink: 3-inch scratch on quartz top. Taped, photo #14."
Before you sign, read the form. Make sure every item you found is on it, that nothing is described as "accepted" that you haven't accepted, and that you leave with a copy. Keep your photos in one album, named by date.
Normal, or a deficiency?
Not everything is a defect. New homes are built with natural materials that dry, shrink and settle, especially through their first heating season. B.C.'s Residential Construction Performance Guide, created by the Province, sets out the minimum performance warranty providers use to evaluate claims, so it's the fair reference point when you and the builder see an item differently. The standard is reasonable workmanship, not perfection. If you're unsure, list it anyway and let the builder respond. It's much easier to take something off a list than to add it later.
After you sign: the next 12 months
- Follow up in writing. Keep a simple log: item, date reported, date fixed. Check each repair before you sign off on it.
- Photograph the home on move-in day, before the boxes come in. It extends your baseline.
- Keep a running list. Some things only show up once you live in a home: a door that sticks in the rain, a tap that drips, drywall cracks as the home dries. Many builders schedule service-request windows, such as at six months or at year-end. Use them.
- Watch the 12-month line. Most defects in materials and labour are covered for the first 12 months. Under the regulation, you must give the warranty provider and the builder written notice, in reasonable detail, within a reasonable time after you discover a defect and before coverage expires. Mark your calendar a couple of months before your first anniversary.
- Act fast on water. If a defect needs immediate attention, such as a leak, the regulation requires you to take reasonable steps to limit the damage. Damage made worse by not acting can be excluded.
Townhouses and condos: your unit vs. common property
In a strata, there are two warranty policies: one for your home and one for the common property. Your walk-through covers your strata lot. Hallways, the roof, the parkade and the building exterior are common property. If you notice something there, raise it with the strata council or the property manager in writing, so it's recorded for the common-property warranty. And because the common-property clock starts with the building's first homes, don't wait. If you're reviewing a newer building's documents, see how I review strata documents.
Should you bring a home inspector?
If your builder allows it, it's worth considering, especially on a detached home or a townhouse. A good inspector checks things most of us won't: attic insulation, ventilation, roof details, grading and drainage, and the mechanical systems. If the builder only allows inspectors after the walk-through, book one before move-in and send their findings to the builder in writing.
Many owners also book a second inspection around the 11-month mark, while the 12-month materials-and-labour coverage still applies. Inspectors I'm comfortable recommending include Ridgeview Home Inspections, Core Property Inspections and Will Inspect. I don't take referral fees. For what different inspections cover, see the home inspections you actually need in BC and the BC home inspection checklist.
Buying resale? It's a different walk-through
On a resale home there's no builder and no deficiency list. You're buying the home in the condition you viewed it, and the 2-5-10 coverage only carries over if the home is still inside its original coverage periods. If you want a look inside before completion, ask about adding a viewing clause to your offer. Then compare the home with what you saw, and make sure included items are still there. For what happens on the day itself, see what happens on closing day in BC.
Buying new in the Tri-Cities
Much of the new construction in the Tri-Cities is on Burke Mountain, with presale townhomes and detached homes completing every year. If you're comparing projects, start with Burke Mountain presale homes, new construction homes in Coquitlam and Coquitlam builders and developers. Weighing new against resale? See presale vs. resale on Burke Mountain.
Frequently asked questions
What is a deficiency walk-through?
It's a joint inspection of a newly built home by the buyer and a representative of the builder, usually shortly before completion or possession. You record anything damaged, unfinished or not working on an inspection report, both sign it, and the builder fixes the items. It's also called a pre-delivery inspection (PDI) or pre-occupancy inspection.
When should I do a deficiency walk-through?
The builder usually schedules it shortly before completion or possession. For some homes, it's worth doing it in two passes: a professional inspection before you remove subjects, so the first round of deficiencies gets documented early, then one more walk-through about 10 days before possession to check the repairs and catch what's left. Anything you miss can go on your list for the one-year warranty.
Is a pre-delivery inspection required in BC?
B.C.'s Homeowner Protection Act Regulation sets the minimum 2-5-10 home warranty coverage but doesn't require a pre-delivery inspection or set how one works. Walk-throughs are standard builder practice and are usually described in your purchase contract or homeowner manual, so ask your builder how theirs works.
What should I bring to a deficiency walk-through?
Painter's tape to mark each item, a charged phone for photos and a flashlight, a phone charger or outlet tester for the outlets, a notepad or floor plan, a tape measure, your finish selections and upgrade list, and a second person to help look and write.
Can I bring a home inspector to my PDI?
It depends on the builder. Some allow an inspector at the walk-through and some only afterwards. Ask well before the appointment. If one isn't allowed at the walk-through, book an inspection before you move in and send the findings to the builder in writing.
What if I find a problem after I move in?
BC's 2-5-10 warranty covers defects in materials and labour for at least 12 months (15 months for strata common property), with longer coverage for certain systems, the building envelope and structure. Give the warranty provider and the builder written notice in reasonable detail, within a reasonable time after you discover the defect and before coverage expires. Cosmetic damage is harder to claim after move-in, because damage caused by owners or third parties can be excluded.
When does the 2-5-10 warranty start on a condo or townhouse?
For your strata lot, coverage starts on the earlier of when you move in or when legal title transfers to you. For the building's common property, it starts when the first home in that building starts its coverage, so later buyers in a building have less common-property coverage left.
How long does a deficiency walk-through take?
It varies with the size of the home and the builder's process. Ask the builder how long they've booked, and don't schedule anything right after. Rushing is the most common reason items get missed.
Sources & Methodology
- Homeowner Protection Act Regulation (B.C. Reg. 29/99), Schedule 3. Minimum 2-5-10 coverage periods (s. 1 to 3); commencement dates for strata lots and common property (s. 5); owner obligations to allow access (s. 9); permitted exclusions, including owner and third-party damage and normal wear and tear (s. 10 and 11); written notice of claims (s. 16); duty to limit damage (s. 17).
- BC Real Estate Association (BCREA). Strata homes carry two home warranty policies, one for the home and one for the common property.
- Residential Construction Performance Guide (Province of B.C.). Minimum performance standards used by warranty providers to evaluate claims.
- Builder homeowner manuals and warranty materials (including Onni and BlueSky Properties). How pre-delivery inspections are run in practice: a guided orientation, a jointly signed inspection report, and later service-request windows.
- Canadian Home Builders' Association. The builder walk-through and orientation before possession.
General information only, not legal or technical advice. Your purchase contract and warranty certificate govern your rights and deadlines. Last reviewed November 16, 2026.
Signed: Craig Johnston, REALTOR® (BCFSA Licence #187645) · Royal LePage Elite West · Helping Tri-Cities families move up