New Town Centre Park Tennis Courts: When They Open & What Happens to the Old Courts
Fencing went up in Town Centre Park the week of October 5. The City is building ten lit tennis courts and a half court north of Trevor Wingrove Way, and the courts you play on today stay open until the new ones are ready. Here’s the timeline, what’s being built, and what the old courts become.
Quick Answer
Coquitlam is relocating and expanding the Town Centre Park tennis courts. The new facility, with 10 full-size courts plus a half court, LED lighting, spectator seating and a new support building, is going in just north of Trevor Wingrove Way on the old recycling depot and works-yard site. Construction started in early October 2026, and the City is targeting a summer 2027 opening. The existing courts stay open until then. After the new courts open, the old courts and clubhouse will be removed and turned into open lawn for events, festivals and picnics.
The project at a glance
| Item | What the City has published |
|---|---|
| Location | Town Centre Park, just north of Trevor Wingrove Way (former recycling depot and East Works Yard) |
| Courts | 10 full-size courts + 1 half court (a net gain of two) |
| Lighting | LED sports lighting |
| Building | New energy-efficient support building replacing the old clubhouse: bookable meeting space, kitchenette, accessible washroom |
| Extras | Spectator seating on the west edge, social patio, drinking fountain and bottle refill station, four accessible parking stalls |
| Construction start | Site fenced from the week of October 5, 2026 |
| Target opening | Summer 2027 |
| Existing courts | Open until the new facility is complete, then removed and turned into open lawn |
| Pickleball | Not included; the facility is tennis-only |
Construction started this month
If you’ve walked the Lafarge Lake loop lately, you’ve probably noticed the new fencing. The City of Coquitlam began setting up and fencing the site the week of October 5, 2026. Council approved the final design in June, and the City’s news release at the time called it “Game, Set, Upgrade.”
The prep work started well before the fences went up:
- February 1, 2026: The Town Centre Recycling Depot closed for good to free up the land.
- February 2026: Trees were cleared from the site south of Percy Perry Stadium before nesting season started on March 1. The City says it removed only what was necessary and will replant with larger, climate-adapted species.
- June 2026: Council approved the final design.
- October 2026: The site was fenced and construction began.
The new courts also take over the City’s East Works Yard. Administrative staff are moving into the Percy Perry Stadium office, and new park maintenance storage is planned for the south end of the stadium.
Why now? Metro Vancouver is replacing a major water main along Pipeline Road, on the east edge of the park, in phases that are expected to run until 2034. The City moved the tennis project ahead of its original master-plan schedule so park users go through one long stretch of construction instead of two.
What’s closed during construction
The construction areas stay fenced while work is under way, and some trails around the new courts are closed. Detour signs mark the alternate routes. The rest of Town Centre Park, including Lafarge Lake, the lake loop, Percy Perry Stadium, the sports fields and the playgrounds, stays open as usual. The City has posted a Phase 1 construction map on its Town Centre Park Upgrades page.
When will the new courts open?
The City’s FAQ says the new courts are expected to open in summer 2027. Its construction schedule supports that: Phase 1 runs from Q4 2026 to Q3 2027, and related park work continues through Q4 (October to December) 2027. In other words, the courts should be playable first, and the clean-up around them, including the conversion of the old courts, finishes afterward.
One caution: the City’s June announcement said construction would start “this summer,” and it actually started in early October. A few months of slippage at the start doesn’t always carry through to the finish, but I’d plan around summer 2027 as a target, not a promise. If you’re a league player or organize a club ladder, keep the 2027 season on the existing courts as your backup plan. The City posts updates at coquitlam.ca/TCPUpgrades.
What happens to the existing tennis courts?
This is the question I get most from people who live around the park, so here’s the short version.
- Until the new courts open, nothing changes. The City says the current courts south of Trevor Wingrove Way stay open for play through construction.
- After the new facility opens, the old courts and clubhouse are removed. The City’s FAQ says this plainly: once the new facility opens in summer 2027, the existing courts and clubhouse come out.
- The space becomes open lawn. The City plans to restore the area as lawn for community events, festivals, games, picnics and informal recreation.
That last part matters more than it sounds. Town Centre Park already hosts Coquitlam’s biggest public events, and the City has spent the last several years building that capacity: the Festival Lawn was expanded in 2019 and the Festival Hub was finished in December 2020. Turning a fenced block of hard courts into open lawn gives the park more flexible event and picnic space, close to the lake. The City’s renderings show the new lawn just south of the new courts.
The City hasn’t published a separate completion date for the lawn conversion. Given the schedule above, late 2027 is a reasonable expectation, but that’s my reading of the phasing, not an official date.
What’s in the new facility
According to the City, the relocated facility will include:
- 10 full-size courts and 1 half court with high-quality playing surfaces. The half court works well for practice and lessons for younger kids.
- LED sports lighting. Citywide, lit public courts are available from sundown until 10 p.m.
- Spectator seating on the west edge, with set-aside spaces for mobility devices and strollers.
- A social patio to the south with movable seating and tables.
- A new support building replacing the old clubhouse, with bookable meeting space, a kitchenette, an accessible washroom and large windows facing the mountains.
- A drinking fountain with a bottle refill station, plus four accessible parking stalls.
- Landscaping and tree planting to blend the facility into the park.
Is there pickleball?
No. The City has confirmed the new Town Centre courts are tennis-only. Pickleball players should look at Bramble Park (2775 Panorama Drive, Westwood Plateau), where the City converted tennis courts into eight permanent, lit pickleball courts in 2022.
What about the Coquitlam Tennis Club?
The City says the Coquitlam Tennis Club keeps priority seasonal access, and the new support building that replaces the old clubhouse is publicly accessible. Outside club priority, City-operated outdoor courts are open for public drop-in play, and private reservations and private lessons aren’t permitted on them.
Where this fits in Coquitlam’s tennis picture
Town Centre is one of three court projects the City is finishing at about the same time. According to a February 2026 City release, Coquitlam had 34 publicly accessible tennis courts (29 outdoor, 5 indoor), and three projects add nine dedicated outdoor courts by 2027:
| Project | New courts | Status |
|---|---|---|
| Burke Mountain Athletic Park (Burke Mountain) | 4 | Opened September 25, 2026 |
| Cottonwood Park (Burquitlam–Lougheed) | 3 | Expected spring 2027 |
| Town Centre Park (City Centre) | +2 net (10 + half court) | Target summer 2027 |
If you live on Burke Mountain, you don’t have to wait. The four courts at the new Burke Mountain Athletic Park are open now. Town Centre is the biggest of the three projects by far, with ten and a half lit courts, seating and a new clubhouse building in one place.
What this means if you live, or want to live, near Town Centre
Let’s be realistic: a new tennis facility won’t move the benchmark price of a Coquitlam condo on its own. But parks like this shape how a neighbourhood feels day to day, and that comes up in almost every conversation I have with buyers looking at the City Centre.
- For buyers: Much of the high-rise inventory around Coquitlam Town Centre and Lafarge Lake–Douglas Station sits within walking distance of the park and the Millennium Line. By 2027 that walk gets you lit courts, a stadium track, turf fields and a bigger event lawn. That’s a real lifestyle advantage over a lot of suburban condo locations.
- For owners near the construction: Expect fencing, trail detours and some construction traffic off Trevor Wingrove Way and Pipeline Road through 2027. The water main work on Pipeline Road is a much longer project, expected to run to 2034. If you’re selling a unit that overlooks the work, schedule photos and showings with it in mind, and tell buyers what’s being built rather than letting them guess.
- For sellers listing in 2027: Once the courts and lawn are finished, they’re a selling point for every nearby listing. A finished, photographed amenity is a much stronger story than a rendering.
If you’re trying to work out what your home near the park is worth now, my Coquitlam Town Centre home value guide is a good place to start.
How I help buyers and sellers around Town Centre
Read the City’s plans with you
Tennis courts, the water main, new towers. I’ll show you what’s planned around a building before you write an offer, not after.
Compare towers, not just units
Strata health, age, views over the park or over the work site. In the City Centre, two buildings on the same block can be very different buys.
Price to this pocket
I anchor to recent sales in the same part of the City Centre, not a Coquitlam-wide average.
Time the listing
If you’re selling near the park, we’ll decide whether to list now or after the new courts and lawn are finished.
Frequently asked questions
When will the new Town Centre Park tennis courts open?
The City of Coquitlam is targeting summer 2027. Site fencing went up the week of October 5, 2026, and the City’s phasing shows the new-court area under construction from Q4 2026 through Q3 2027, with related park work continuing through Q4 (October to December) 2027. Construction started a few months later than the City’s June 2026 announcement suggested, so treat summer 2027 as a target rather than a promise.
Can I still play on the existing Town Centre Park tennis courts during construction?
Yes. The City says the current courts south of Trevor Wingrove Way stay open for play until the new facility is complete. Some trails around the construction area are closed, so follow the detour signs.
What will happen to the old tennis courts at Town Centre Park?
Once the new facility opens, the City will remove the existing courts and the old clubhouse and turn that area into open lawn for community events, festivals, picnics and informal recreation. The City hasn’t published a separate date for that conversion.
Where are the new tennis courts being built?
Just north of Trevor Wingrove Way, on the site of the former Town Centre Recycling Depot (closed February 1, 2026) and the City’s East Works Yard, south of Percy Perry Stadium.
How many courts will the new facility have?
Ten full-size courts and one half court, with LED sports lighting. The City describes it as a net gain of two courts over the current facility.
Will the new courts have pickleball lines?
No. The City says the new Town Centre facility is dedicated to tennis. For pickleball, the City converted the tennis courts at Bramble Park (2775 Panorama Drive, Westwood Plateau) into eight permanent pickleball courts.
What happens to the Coquitlam Tennis Club?
A new, publicly accessible support building replaces the aging clubhouse, with meeting space, a kitchenette and an accessible washroom. The City says the Coquitlam Tennis Club keeps priority seasonal access.
Why is the City building the courts now?
Metro Vancouver’s multi-phase Coquitlam Water Main Project along Pipeline Road, on the park’s east edge, is expected to run until 2034. The City moved the tennis project earlier than the master plan originally set so park users face one stretch of disruption instead of two.
Sources & Methodology
Every project detail in this post comes from the City of Coquitlam’s own publications, with local news used only for background:
- City of Coquitlam — Town Centre Park Upgrades (coquitlam.ca/TCPUpgrades). Source for: court count, the October 5, 2026 site set-up, the Phase 1 schedule (Q4 2026 to Q3 2027), work continuing through Q4 2027, the lawn conversion, and the five renderings used in this post.
- City of Coquitlam — Town Centre Park FAQ (coquitlam.ca). Source for: the summer 2027 opening target, existing courts staying open, removal of the old courts and clubhouse, Coquitlam Tennis Club priority access, the no-pickleball decision and Bramble Park.
- City of Coquitlam — “Game, Set, Upgrade” news release (June 24, 2026). Source for: Council design approval, the support building, patio and seating, the East Works Yard relocation, and trail detours.
- City of Coquitlam — Recycling Depot closure release (January 8, 2026). Source for: the February 1, 2026 depot closure, the site location, and the Metro Vancouver water main timing (to 2034).
- City of Coquitlam — Cottonwood Park tennis release (February 17, 2026) and the Tennis & Pickleball Courts page. Source for: citywide court counts, the three-project expansion, lighting hours and drop-in rules.
- Background: Tri-Cities Dispatch (Jan. 12, 2026) and Freshet News (Feb. 18, 2026) coverage of the site clearing and the project.
Methodology: Facts were checked against the City pages above on October 11, 2026. Where City sources give different timing (a “summer 2026” start in June versus the actual October start), this post reports both and treats summer 2027 as a target. Opinions about what the project means for nearby homeowners are my own, based on working the Coquitlam market. Renderings © City of Coquitlam, shown for information; they are conceptual and the final design may vary.
Signed: Craig Johnston, REALTOR® V99960 · Royal LePage Elite West
Thinking about buying or selling near Town Centre Park?
The City Centre isn’t one market. It’s a set of towers, townhome pockets and Westwood-edge streets, each priced differently. I’ll show you what’s being built around a home, pull the right comparables, and help you time the move.
Direct: 604-202-6092 · Craig@SoldByCraig.ca